Pawel's MPANMPRN Lifecycle

The life of a GB electricity or gas supply point
Lifecycle Vol. 01
November · 2026

Follow the MPANMPRN from the day a property is connected to the day it's cut off for good, as it is created, registered, lived through and finally retired. Scroll down to move through time; open any stage for the detail and its source.

The vertical line is the MPAN. Its colour is the supply's state. Forming New Live De-energised · reversible Disconnected · permanent
The vertical line is the MPRN. Its colour is the supply's state. Forming New Live Dead · reversible Disconnected · permanent
01 · BIRTH

Getting connected

Before a home or business can have an MPAN (Meter Point Administration Number, its electricity supply number), it needs a physical cable from the local electricity network. The industry calls this a "new connection", and it happens in four steps: apply, receive a quote, build it, and then the number is created.

Step 1 · Birth

Application

Whoever wants power asks the local network for a connection and says how much electricity the site will need.

This is the first step, before any identifier exists. Whoever wants power at a site, whether a housebuilder or a homeowner, asks the local network company for a connection and says how much electricity the site will need at its busiest. That size is measured in kVA (kilovolt-amperes, roughly how much power the connection can carry at once). Getting it right matters, because it decides how big the cables and equipment must be, and so what the connection costs.

  • Early on, before a project is certain (no firm build date yet, or the applicant does not own the land yet), the network can give a budget estimate instead of a full design. It is a quick, rough price that lets a developer check the idea is affordable before committing. A formal application follows once the project is going ahead.
  • A typical home gets a single-phase supply protected by a 100A main fuse, which can carry about 23 kVA at 230 V. If a property's expected peak (its after-diversity demand, explained below) is above roughly 23 kW, it gets a three-phase supply instead, which can carry more.
  • A housing estate is not sized by adding up every home's maximum, because homes rarely all peak at the same moment: one household is cooking while the next is out. The network instead uses ADMD (after-diversity maximum demand), a standard allowance per home that reflects this, to size the shared cables, transformers and substations.
  • Bigger or unusual connections need more checks. Above 69 kVA the current is too large to pass straight through the meter, so it is measured through a current transformer (CT), which feeds the meter a small, proportional copy of the current. A site that will also generate electricity, such as solar panels or a battery that exports, must give extra technical detail. If a generator could affect the national high-voltage grid (the transmission system), the local network company, the DNO (Distribution Network Operator), refers it to NESO (the National Energy System Operator) for a Statement of Works, an assessment of its impact on the wider grid.
Sources: INA — Low Voltage Design Policy (ETSC-DES-001) (ADMD, the 100A / three-phase threshold, 69 kVA CT metering); SSEN — generation connection network processes (the Statement of Works); NESO — role in connections (the transmission-level referral for generation); National Grid — budget estimate (an early cost indication before a full quotation).
Context · not part of the domestic journey

The connections queue reform (TMO4+)

Large projects that affect the national grid, mostly generators and batteries, wait in a national connection queue, which was overhauled in 2025. Connecting a normal home is not part of it.

This box steps aside from the normal journey to explain a reform you will hear about constantly in the industry, and why it does not apply to a home.

  • The problem: by December 2024 the queue held around 739 GW (gigawatts) of projects wanting to connect, roughly four times what the system needs for 2030. Much of it was "zombie" projects that had reserved a place without really progressing. Places were given out first come, first served, so projects that were ready to build were stuck behind stalled ones.
  • The fix, known as TMO4+, changes the rule to "first ready and needed, first connected". To earn a firm connection date (a Gate 2 offer), a project must pass a Readiness test, chiefly showing it has secured the rights to its site, and a Strategic Alignment test, showing it fits the mix of generation the country plans to need. Ofgem approved the package on 15 April 2025 and it took effect on 10 June 2025.
  • Since then the queue has been reordered, and revised connection offers are being issued in phases, a process NESO expects to run to March 2027.
  • Why it sits to the side here: the reform covers large projects whose connection affects the national transmission grid. Most are generators and batteries, including some that connect to local networks. Connecting an ordinary home or small business to the local network is not part of it, and follows the simpler journey on the main line.
Sources: Ofgem — TMO4+ Summary Decision Document (the approval and the two gating tests); Ofgem — reforming the connections process (the 739 GW queue, Dec 2024); NESO — Connections Reform (the queue at around four times the 2030 need; Gate 2); NESO — summer system update slide pack (June 2026) (offers issued in phases to March 2027).
Step 2 · Birth

Quotation & offer

The network works out how to connect the site and what it will cost, and the customer chooses who will build it.

With the application in, the network designs the connection and sends a formal offer setting out the price. Two decisions made here shape the whole job: where the new cable joins the existing network, and who is allowed to build which parts.

  • The offer fixes the Point of Connection, the spot where the new cable meets the existing network. It also splits the cost into two kinds. Extension work is the cable and equipment that serve only this site, and the customer always pays for it. Reinforcement is upgrading the shared network so it can carry the extra load.
  • There are two ways to get it built. Either the DNO does all the work, or an ICP (Independent Connection Provider, an accredited contractor) builds the new network, which is then handed over to the DNO or to an IDNO (Independent Distribution Network Operator) to own and run. This choice is what the industry calls "competition in connections". Work that may be opened to competition is contestable; work that must stay with the DNO, such as the final connection to its live network, is non-contestable.
  • Who pays for reinforcement changed in 2023, when Ofgem reformed connection charging through the Access SCR (a Significant Code Review). A connection that takes power, such as a home, now generally pays nothing towards reinforcement unless the cost is unusually high: above £1,720 per kVA, the customer pays the excess. The rest is spread across everyone's network charges, which made ordinary connections cheaper.
Sources: Ofgem — Access & Forward-Looking Charges SCR decision (extension vs reinforcement; the £1,720/kVA High Cost Cap); DCUSA — Schedule 22 (Common Connection Charging Methodology); National Grid — ICP and IDNO customers (the contestable / ICP / IDNO delivery route).
Step 3 · Birth

Physical works & energisation

The cables are laid and switched on, up to the main fuse where the meter will go.

This is where the connection is built and switched on. At the end of it there is live power at the property, but still no meter and no MPAN.

  • The digging, cable-laying and any new substation are done by the DNO or, on the competition route, by the ICP for the contestable parts. Even then, the DNO makes the final connection to its own live network.
  • The supply is then energised (made live) up to the cut-out, the sealed unit holding the main fuse, where the network's cable ends and the property's own wiring begins. Power is now available there, ready for a meter to be fitted.
  • On the competition route the finished network is handed to its new owner under an Adoption Agreement. Where that owner is an IDNO, it has usually won the estate by paying the developer an "asset value": an upfront sum for the right to own the network and collect its future network charges. Gas works the same way with independent gas transporters, shown on the gas track.
Sources: Scottish Government — research on connection costs (adoption and the "asset value" model, recovered through DUoS); INA — Low Voltage Design Policy (energisation up to the cut-out); RPC — securing electricity for developments (the DNO-only vs ICP / IDNO delivery route).
Step 4 · Birth · the identifier is born

MPAN created STATE: NEW

The network gives the new supply point its MPAN, a 13-digit number that identifies it for life. The thread begins here.

This is the moment the supply point gets its permanent name. Almost everything that follows, from registration and metering to billing and switching supplier, uses this number. Think of it as a permanent address for one electricity supply: it names the place, not the equipment or the people living there.

  • The network company creates the MPAN. Usually that is the regional DNO, which owns the local wires. Where an IDNO owns the cables on a new estate, the IDNO issues it instead. The first two digits identify the network operator, so IDNO numbers start with their own codes, a quick way to tell that a site is on an independent network.
  • The number is recorded in the network's registration service, MPAS (Meter Point Administration Service, run on a system called MPRS). No supplier has taken it on yet, so it is a meter point that exists but is unregistered. It also shows up in the industry's look-up service, the Electricity Enquiry Service (EES, also known as ECOES), which is how suppliers and brokers find a supply point before registering or quoting for it.
  • The MPAN identifies the supply point, the place electricity is delivered, not the meter. That is why it stays with the property for life: the meter can be replaced and the customer can change supplier many times, and the MPAN stays the same.
  • What most people call "the MPAN" is printed on a bill as a two-line box called the Supply Number. The bottom line is the MPAN itself, 13 digits: a 2-digit distributor code, a 10-digit unique reference and a final check digit. The top line, 9 digits, describes how the supply is set up for settlement and charging. Together the two lines make 22 digits. The 13-digit MPAN never changes; the top line can.
  • The top line changed format for every MPAN on 22 September 2025, under R0083, a change to the industry's Retail Energy Code, as part of the move to half-hourly settlement (MHHS). It now holds three codes. The 2-digit Profile Class says what type of customer this is, which is used to estimate when a supply without half-hourly readings uses its electricity. The 4-digit Standard Settlement Configuration (SSC) Id, which replaced the older 3-digit Meter Timeswitch Code, describes the meter's registers and when each one records. The 3-digit DUoS Tariff Id sets the site's distribution charges (DUoS, Distribution Use of System, is the charge for using the local network); for supplies not yet moved to half-hourly settlement, that slot still carries the older Line Loss Factor Class. Where a code no longer applies, as can happen for a smart meter settled on its half-hourly readings, it is shown as zeros (00 or 0000).
  • A rival proposal, R0083A, would have removed the top line altogether, matching gas, which has no such line. Ofgem rejected it because suppliers and brokers use the top-line codes to quote prices, and larger businesses read the DUoS Tariff Id to see which distribution charges apply to them.
The 22 digits of a Supply Number, in the layout used since 22 September 2025 · tap or hover any part to see what it means
Top line9 digits · how the supply is set up
Bottom linethe 13-digit MPAN · permanent

Tap or hover a segment above to see what those digits mean.

Sources: SSEN — "What is an MPAN?" (what the MPAN is, the two-line Supply Number, IDNO prefixes); Elexon — MSID/MPAN guidance (the MPAN as the supply-point identifier and its registration states; MPAS and MPRS); Xoserve — A–Z (the parallel MPRN and its status model); Ofgem — decision approving REC R0083, "Changes to Supply Number Format for MHHS" (17 Nov 2023) (the new top-line codes for every MPAN from milestone M8; the zero codes; the rejection of R0083A); RECCo — EES portal demo for MHHS (the nine-digit top line over the 13-digit core); Elexon — glossary: Electricity Enquiry Service (EES, also known as ECOES).
02 · MARKET ENTRY

Entering the market

A brand-new MPAN does nothing until a supplier takes it on. This phase is where it becomes a live supply: billed to a customer and counted in the market's accounts.

Step 5 · Market entry

First registration STATE: NEW → LIVE

A supplier takes the MPAN on for the first time and the site starts trading.

A brand-new MPAN sits unused until a supplier claims it. Registration turns a physically connected site into a supply that is billed to a customer and counted in the market.

  • The customer chooses an electricity supplier, and that supplier registers the MPAN in its own name through the central registration systems. A first registration usually takes longer than an ordinary switch, often several weeks, because the supply point is new to the market and its details have to be set up from scratch.
  • The supply's details, including that it is energised (switched on), are recorded in the industry's data, so it starts being included in settlement: the process, run centrally by Elexon, that works out how much electricity each supplier's customers used in every half hour. From 28 October 2026 (MHHS milestone M14), every new connection joins the new half-hourly arrangements straight away.
  • With that done the supply point moves from new to live, and the thread on this page turns green. From here on it is a fully trading supply: metered, settled and billed.
Sources: Retail Energy Code — the services we manage (registration & the Central Switching Service); Ofgem — end-to-end switching arrangements (supply-point creation, first registration); MHHS Programme — Migration Thresholds Document (all new connections under MHHS from M14).
Step 6 · Market entry

Metering & data

The supplier appoints the specialists who fit the meter and collect its readings. This is the layer MHHS is rebuilding.

Once the supply is live, specialist companies look after the meter and feed its readings into settlement, the process that works out how much electricity each supplier's customers used, so that each supplier pays for the right amount of wholesale energy. MHHS (Market-wide Half-Hourly Settlement) is the programme rebuilding this layer. Under the old rules most homes were settled on an estimated daily pattern of use. Under MHHS, a home with a working smart meter is settled on what it actually used in each half hour, while a home without one is still estimated, using patterns built from real half-hourly data. The move is well under way: more than half of all MPANs had switched over by summer 2026.

  • In the old model, four specialists sit behind the supplier. The MOP (Meter Operator) fits and maintains the meter. The DC (Data Collector) collects its readings. The DA (Data Aggregator) adds up the readings across all the supplier's customers and passes the totals into settlement. The MAP (Meter Asset Provider) owns the meter and rents it to the supplier.
  • MHHS renames and regroups these jobs as services, organised by type of meter. Fitting and maintaining meters becomes a Metering Service: MSS (Smart) for smart and non-smart meters, and MSA (Advanced) for the half-hourly meters at larger sites. Collecting readings becomes a Data Service: SDS (Smart), ADS (Advanced) or UMSDS (Unmetered Supplies, for things like street lights that have no meter).
  • The biggest change is in adding up the numbers. Instead of each supplier's Data Aggregator doing it privately, one central system run by Elexon, the Market-wide Data Service (MDS), does it for the whole market, and the Volume Allocation Service (VAS) assigns the totals to each supplier's settlement accounts (BMUs, Balancing Mechanism Units). A new role, the Meter Data Retriever (MDR), collects half-hourly readings from smart meters through the DCC (Data Communications Company), the national network every smart meter talks to. A supplier can run the MDR itself or hire someone to do it.
  • This matters most for ordinary homes. Under the old rules a home is not read half-hourly, so settlement puts it in one of eight Profile Classes (01 is a single-rate home, 02 a home with Economy 7), each a standard pattern of use built years ago from a sample of monitored sites, and assumes the home follows that pattern. MHHS replaces those old patterns. The new Load Shaping Service (LSS) builds patterns from the market's real half-hourly data, and a processing service turns each meter's readings into half-hourly values. A smart-metered home is then settled on what it actually used, half hour by half hour, rather than on an average.
  • Because settlement no longer needs to separate half-hourly meters from the rest, the old Measurement Classes A to G are replaced by three Market Segments: Smart (which also covers non-smart meters), Advanced and Unmetered. The reference data behind all these codes, Market Domain Data (MDD), is being replaced by Industry Standing Data (ISD); the two run side by side during the changeover.
  • Settlement also finishes sooner. Today, the settlement timetable, the series of runs that gradually replace estimates with real readings, takes about 14 months to complete. Under MHHS it falls to about four months from July 2027 (milestone M16), so suppliers spend less time exposed to estimated figures. Elexon expects to process up to 500 billion half-hourly readings a year once migration completes in May 2027.
Sources: MHHS Programme Glossary (MHHS-DEL257 v1.2, Elexon, Nov 2025) (the MHHS roles and services: Metering/Data Services, MDS/VAS, the MDR, Load Shaping, Market Segments, ISD); Elexon — MHHS and the BSC (what MHHS is; the settlement timetable falling to about four months; 500 billion readings a year); Elexon — Profiling (how the eight Profile Classes and Load Profiles are built).
Context · the reform running underneath all of this

MHHS: where the programme stands

In Elexon's words, Market-wide Half-Hourly Settlement is the largest change to the electricity retail market since competition began. Ofgem sponsors it, and Elexon runs it as Senior Responsible Owner and Implementation Manager.

This box steps off the supply point's own journey to explain the programme behind so many of the steps above: what it delivers, and when.

  • What it does: it moves homes and small businesses onto half-hourly settlement. Larger business sites were moved years ago by an earlier change to the Balancing and Settlement Code, P272, so MHHS finishes the job for everyone else.
  • Key dates so far: the industry code changes (M8) took effect on 22 September 2025, and the new central systems were confirmed ready (M10) two days later. Migration began on 22 October 2025 (M11 and M12), and more than half of all MPANs had moved by summer 2026. Still to come: 28 October 2026 (M14), the deadline for every supplier to be qualified and operating under MHHS; 7 May 2027 (M15), when migration completes; and 2 July 2027 (M16), when the faster settlement timetable starts.
  • The M14 deadline has teeth. A supplier that is not qualified by then loses the ability to take on new customers until it is. M14 also ends reverse migration: until then a migrated MPAN can move back to the old arrangements on a change of supplier, but after it there is no way back.
  • Migration is deliberately paced so the market is not overwhelmed. A central Migration Control Centre plans for 200,000 MPANs a day, with an absolute ceiling of 300,000.
  • Ofgem's business case put the net benefit to consumers at around £1.6bn to £4.5bn between 2021 and 2045, largely because half-hourly settlement lets suppliers offer time-of-use tariffs that reward customers for using electricity off peak.
Sources: Ofgem — MHHS Decision & Full Business Case (the £1.6–4.5bn net benefit, 2021 to 2045); Ofgem — MHHS Final Impact Assessment (the benefit and cost modelling); MHHS Programme Glossary (MHHS-DEL257 v1.2); MHHS Programme — Qualification Approach & Plan (the migration cap); MHHS Programme — Key Programme Milestones (milestone dates; the M14 deadline and the end of reverse migration); MHHS Programme — News Hub (half of all MPANs migrated).
03 · LIFE

Living in the market

Most of a supply point's life is spent here: being switched, changing hands and having its meter replaced, all without a new connection.

Step 7 · Life

Switches, tenancies & meter changes

The everyday changes a live supply goes through over the years.

Most of a supply point's life is uneventful. It carries on delivering power while ownership, supplier and hardware change around it. None of the events below creates a new MPAN; the same identifier simply passes between parties.

  • A change of supplier goes through the Central Switching Service (CSS), the national system that moves a supply point from one supplier to another. Suppliers must complete a switch within five working days, and many are faster. The customer still has 14 days to change their mind, and the old supplier can object on grounds of debt only in tightly limited cases.
  • A change of tenancy happens when the people living there change, for example when a house is sold or let. The new occupier is placed on a deemed contract (the supplier's standard terms until they choose a tariff). The supply itself carries on, and the new occupier does not take on the previous occupier's debt.
  • Meter exchanges, including the smart-meter rollout, replace the physical meter, but the MPAN is unchanged because it names the supply point rather than the meter. When a customer is switched by mistake, the move is reversed under the industry's Erroneous Transfer process, which puts them back with the original supplier as if it had not happened.
Sources: Retail Energy Code — the services we manage (the CSS five-day switch, cooling-off, change of tenancy, meter changes and Erroneous Transfer); Electricity Act 1989 (the deemed-contract basis).
04 · DEATH

Winding down

Winding down runs from a switch-off that can be undone, to a permanent physical disconnection, and finally the retirement of the MPAN itself.

Context · a common misconception

Being cut off for debt is now rare

The disconnection most people picture, being switched off for non-payment, is now a genuine last resort. Most real end-of-life is physical: refurbishment, demolition or leaving the network.

People tend to picture "disconnection" as a supplier cutting off a customer who has not paid. In practice that is now very rare, and it helps to understand why before looking at how a supply is really wound down.

  • Ofgem treats access to energy as an essential service, so licence conditions make disconnection for debt a genuine last resort. A supplier must first offer alternatives such as Fuel Direct (deductions straight from benefits), a repayment instalment plan, or a prepayment meter.
  • After a 2023 scandal in which suppliers forced prepayment meters into vulnerable homes, including under court warrants, fitting one without the customer's agreement is now tightly restricted. Ofgem's rules, part of every supplier's licence since 8 November 2023, require at least ten attempts to contact the customer and a welfare visit first, and ban forced installations altogether for the most vulnerable households.
  • Cost is the other side. Debt that is never recovered is spread across everyone's bills, so the balance between protecting individuals and controlling that shared cost is contested. Ofgem has been evaluating how well the 2023 rules work, and said it would conclude that review in the first half of 2026.
Sources: Ofgem — Involuntary PPM Code of Practice (disconnection for debt as a last resort; the welfare and "do not install" protections); Ofgem — enhanced PPM rules (Nov 2023) (the ten contact attempts and welfare checks); Ofgem — debt strategy update (the evaluation of the 2023 rules, due to conclude in the first half of 2026).
Step 8 · Death · reversible

De-energisation STATE: DE-ENERGISED

A temporary switch-off: the main fuse is removed, but the property stays connected.

The first stage of winding down is a pause rather than an ending. The supply is switched off but the physical connection stays in place, so it can be brought back later without a new connection. This is the amber state on the thread.

  • The customer arranges it through their supplier, whose meter operator removes the main fuse from the cut-out so no current can flow (the network company can also do this). It suits situations like a refurbishment or a property standing empty between occupiers.
  • It is fully reversible: because the service cable stays in the ground, the supply can be re-energised later without rebuilding anything.
  • Standing charges can keep running while a supply is de-energised, so if the pause is likely to be long, the meter is often removed as well.
  • One MHHS-related change affects de-energised sites. From 1 April 2027, under an industry change called DCP440, a migrated MPAN that is recorded as de-energised but is actually using electricity will pay distribution charges (DUoS) from the moment that use is detected. This closes a gap where such sites avoided those charges, leaving everyone else to pick up the cost.
Sources: National Grid — disconnections (de-energisation is reversible); Electricity North West — guidance on temporary de-energisation (arranged through the supplier, whose authorised agent removes the cut-out fuse); Ofgem — DCP440 decision (DUoS on consuming de-energised sites from 1 April 2027).
Step 9 · Death · the point of no return

Disconnection STATE: DISCONNECTED

The permanent cut: the service cable is removed.

Disconnection is the permanent version, and the point of no return on the thread. Where de-energisation pulls the fuse, disconnection physically removes the service cable that joins the property to the network.

  • Only the DNO or IDNO that owns the network may carry this out. It is unlawful for anyone else to disconnect a property from the mains, because it means working on live network equipment.
  • It is used when a property no longer needs a supply, most commonly before demolition or a major redevelopment.
  • There is no quick way back. To restore power to the site afterwards you have to apply for a brand-new connection, which loops right back to the first step at the top of this page and creates a fresh MPAN.
Source: National Grid — permanent disconnection (removing the service cable; DNO/IDNO only; a new connection needed to restore supply).
Step 10 · Death · retirement

MPAN retirement STATE: RETIRED

The identifier is retired and the meter removed. The thread ends.

The final step closes the record. Once a supply is permanently disconnected, its identifier is retired and the physical hardware taken away, and the thread on this page ends.

  • A disconnected MPAN is retired; because each MPAN is a unique, permanent identifier, a future connection at the same address gets a new one, so there is no risk of old billing or settlement history attaching to it.
  • The meter is physically removed, so no further standing charges build up against a supply that no longer exists.
  • Where a building is being demolished, disconnecting the supply and removing the meter first is legally required, because live cables and meters left in a demolition site are a serious safety hazard.
Sources: National Grid — disconnections (retirement and meter removal); Elexon — MSID/MPAN guidance (the MPAN as a unique, permanent identifier); NFDC — Disconnection of Services (DRG108) and CDM Regulations 2015 (services isolated before demolition).
01 · BIRTH

Getting connected

Before a property can have an MPRN (Meter Point Reference Number, its gas supply number), it needs a physical gas pipe from the network, laid either by the regional gas network company or by an independent one. As with electricity, this happens in four steps: apply, receive a quote, build it, and then the number is created.

Step 1 · Birth

Application

Whoever wants gas asks the network (or an independent connector) for a connection and says how much gas the site will use.

This is the first step on the gas side, before any MPRN exists. Whoever wants a gas supply asks for the property to be connected, and the network checks there is enough gas, at enough pressure, to serve it. The names differ from electricity: the regional network here is a GDN (Gas Distribution Network, the company that owns the local pipes), and on new estates the work is often done by an independent connector instead.

  • The network checks whether the nearest gas main has enough pressure and spare capacity for the new site, or needs reinforcing first, then surveys the site and issues a quote. Where a pipe already exists, for example when a property wants more gas than before, the standard request for that pipe's pressure and capacity is known as a GT1.
  • The connection is sized by the meter. A home takes a U6 meter, the standard domestic size, while commercial and industrial sites use larger meters (U16 and above). Behind that, the site's demand is described by its AQ (Annual Quantity, how much gas it is expected to use in a year) and its SOQ (Supply Offtake Quantity, how much it can take on its busiest day).
  • Bigger sites need more detailed checks on whether the network can carry their demand. The very largest, such as power stations and big industrial plants, connect straight to the National Transmission System, the high-pressure national gas grid, as directly-connected sites.
Sources: Cadent — new gas connection (the connection journey); Cadent — GT1 survey (pressure and capacity information for an existing pipe); Xoserve — A–Z (AQ and SOQ); National Gas Transmission — our network and assets (the largest users are directly connected to the NTS).
Context · not the standard GDN journey

Independent networks (iGTs) & the "asset value" route

On many new housing developments the gas pipes are owned by an independent gas transporter rather than the regional network. It is the gas version of the independent electricity networks (IDNOs) on the other track.

This box steps aside from the standard journey. On new-build estates the gas pipes are often owned by an independent company rather than the regional GDN, which changes who builds the connection and how it is paid for.

  • An iGT (Independent Gas Transporter) owns and runs the pipes on the development. They are built by a UIP (Utility Infrastructure Provider), the gas counterpart of an electricity ICP (Independent Connection Provider). A UIP must be accredited under GIRS (the Gas Industry Registration Scheme), which LRQA runs on behalf of the gas transporters.
  • The point where an iGT's network joins the regional network is a CSEP (Connected System Exit Point). The CSEP has to be set up on UK Link, the central gas registration system run by Xoserve, before the iGT can create a meter point for each plot.
  • The money works like the electricity asset-value model. The developer pays less upfront, often around £400 to £900 per plot, and the iGT recovers its investment over time through the transportation charges built into residents' gas bills.
Sources: LRQA — Gas Industry Registration Scheme (GIRS) (UIP accreditation for contestable works); Xoserve — Supply Point Administration (CSEPs on UK Link).
Step 2 · Birth

Quotation & offer

The network designs the connection and prices it, separating the work only it may do from the work others can compete for.

With the checks done, the network designs the connection and prices it. As on the electricity side, the work divides into parts only the network may do and parts that can be opened to competition. The charging rules differ, though: gas has not had the reform that made most electricity reinforcement free to the customer.

  • Non-contestable work, the final connection to the live gas main, must stay with the GDN because it means working on the network itself. Contestable work, such as laying pipe across private land and the digging that goes with it, can be done by an accredited UIP instead.
  • The customer pays for the service pipe and any extension of the main needed to reach them. The price depends mostly on the distance to the nearest suitable main, since a longer run means more pipe and more digging.
  • Gas connection charges are set under each transporter's own charging arrangements. There is no gas equivalent of electricity's 2023 charging reform (the Access SCR), so gas has not moved to a model where the network pays for most reinforcement, and the customer still bears more of that cost.
Sources: Ofgem — gas & electricity connections Q&A (contestable vs non-contestable); LRQA — becoming a GIRS-accredited UIP (LRQA runs GIRS for the gas transporters); Cadent — new gas connection (service-pipe charges).
Step 3 · Birth

Physical works & connection

The pipe is laid from the gas main to the property, ending at the valve where the meter will be connected.

This is the build stage on the gas side. The pipe is laid up to the property and ends at a valve that marks where the network's responsibility stops.

  • The network, or the UIP on an independent network, lays the service pipe from the main to the property over the following weeks. It ends at the Emergency Control Valve (ECV), the lever that lets anyone in the property shut off the gas in an emergency.
  • The ECV is where responsibility changes hands. The gas network owns and maintains everything up to it, including the main and the service pipe. The meter belongs to the supplier (in practice, the company it rents the meter from). The pipework from the meter to the cooker and boiler belongs to the property owner, who must have it worked on only by a Gas Safe registered engineer. The ECV is the gas equivalent of the electricity cut-out on the other track.
Source: Cadent — new gas connection (the network responsible up to the ECV; the supplier owns the meter; the property owner is responsible for the pipes after it).
Step 4 · Birth · the identifier is born

MPRN created STATE: NEW

The network gives the new gas supply point its MPRN, the number that identifies it for life. The thread begins here.

This is where the gas supply point gets its permanent name, the MPRN (Meter Point Reference Number). It does for gas what the MPAN does for electricity: think of it as a permanent address for one gas supply, which outlasts any meter or supplier.

  • Who creates it depends on who owns the pipes. On a regional network (a GT, or Gas Transporter, network), the GDN creates the MPRN as part of the connection. On an independent network, the iGT creates it once the site's CSEP has been set up on UK Link.
  • Like the MPAN, the MPRN identifies the supply point, not the meter, so it stays with the property for life through meter swaps and changes of supplier. A useful clue: MPRNs on independent networks typically begin 74 or 75, which shows the site is not on the regional network.
  • One common mistake to avoid: a brand-new connection does not use Xoserve's M Number Creation service. That service only exists to create a record for a supply that is already live but has somehow gone missing from UK Link. A new-build MPRN comes through the connection route described above.
Sources: Xoserve — Supply Point Administration (how the MPRN is created); Xoserve — M Number Creation ("not a service for new connections"); Xoserve — A–Z (the MPRN as a permanent identifier and its status model); Elexon — MSID/MPAN guidance (the parallel MPAN identifier).
02 · MARKET ENTRY

Entering the market

Gas has an extra player that electricity doesn't: the shipper. This phase is where a supplier and its shipper take the new MPRN on, and it becomes a live supply.

Step 5 · Market entry

First registration STATE: NEW → LIVE (LI)

A supplier, with its shipper, takes the MPRN on for the first time and the site starts trading.

This is the gas version of first registration. It turns a newly created MPRN into a live supply, and it introduces the one player with no electricity equivalent: the shipper.

  • Gas has a longer chain than electricity: customer, then supplier, then shipper, then transporter. The shipper is the company that buys gas and pays the network to carry it on the supplier's behalf, and every supplier works with one. There is no shipper in electricity.
  • For a home, registration is a single step. The supplier registers the MPRN through the Central Switching Service (CSS), the same national system used for electricity, and Xoserve, which runs the gas registration system UK Link, records the supplier's shipper against the supply point.
  • Bigger sites can add an earlier step called nomination. The shipper asks Xoserve for the site's details and charges, and Xoserve returns a Supply Point Offer that is valid for six months. It is expected for the largest, daily-read sites and optional for other sites using more than 73,200 kWh a year. Either way, once registration completes the meter point status on UK Link becomes Live (LI), and the thread turns green.
Sources: Xoserve — Supply Point Administration (registration and the Supply Point Offer); Xoserve — CSS Supply Point Administration FAQs (suppliers register new gas sites through the CSS); Xoserve — SwitchStream (when nomination is needed; offers valid for six months); Ofgem — change-of-supplier nomination (gas) (the 73,200 kWh larger-site threshold).
Step 6 · Market entry

Metering & data

The supplier appoints the company that looks after the meter, and the site's expected yearly use is updated from its readings.

Once the supply is live, the metering and data arrangements keep it read and correctly charged. The roles have different names from electricity, and gas has no equivalent of the MHHS overhaul under way.

  • The MAM (Meter Asset Manager) looks after the meter and, on larger sites, the volume corrector (a device that adjusts the measured volume for temperature and pressure). A Meter Reading Agent collects the readings. If no reading arrives for too long, a "Must Read" visit is triggered to get an actual one.
  • The AQ (Annual Quantity), the site's expected yearly use, is first set at connection and then recalculated every month whenever a valid new meter reading arrives. It matters because it does two jobs: it decides how much of the gas flowing through the network each day is assigned to this site, and a snapshot of it taken each December sets the site's transportation charges for the following year. An inaccurate AQ feeds straight through to charges.
  • When a meter is fitted or changed, the update goes to Xoserve as a standard RGMA message (Review of Gas Metering Arrangements). Because gas has no MHHS-style overhaul, this layer is far more stable than the one being rebuilt on the electricity track.
Sources: Xoserve — A–Z (AQ, MAM, RGMA); Xoserve — introduction to AQ (the rolling monthly AQ); Xoserve — AQ and SOQ calculations (the December snapshot used for charging); Retail Energy Code — the services we manage (a change of supplier also moves the shipper).
03 · LIFE

Living in the market

The same everyday changes as electricity (switching supplier, changing hands and meter swaps), with the shipper moving alongside the supplier.

Step 7 · Life

Switches, tenancies & meter changes

Over its life the supply is switched, changes hands and has its meter swapped, all without a new connection.

As with electricity, most of a gas supply point's life is routine. It keeps delivering gas while the supplier, occupier and meter change around it, and the MPRN stays the same throughout. The gas twist is that the shipper changes whenever the supplier does.

  • A change of supplier goes through the Central Switching Service, with the same rules as electricity: the switch must complete within five working days, the customer has 14 days to change their mind, and debt objections are tightly limited. The new supplier's shipper takes over as part of the same move.
  • A change of tenancy puts the new occupier on a deemed contract (the supplier's standard terms until they choose a tariff), and the new occupier does not take on the previous occupier's debt.
  • Meter exchanges, including the smart-meter rollout, swap the physical meter, but the MPRN is unchanged because it identifies the supply point and not the meter.
Sources: Retail Energy Code — the services we manage (the CSS five-day switch, cooling-off, change of tenancy, meter changes and Erroneous Transfer); Gas Act 1986 (the deemed-contract basis).
04 · DEATH

Winding down

Winding down runs from capping the supply, which can be undone, to cutting the pipe permanently, and finally the retirement of the MPRN itself.

Context · a common misconception

Being cut off for debt is now rare

As with electricity, cutting a customer off for non-payment is a last resort. Most real end-of-life is physical: switching away from gas, or demolition.

This is the same point made on the electricity side, and the rules are shared across both fuels. Disconnection for debt is a last resort, so end-of-life for a gas supply is almost always physical: the property switches away from gas or is demolished.

  • Ofgem treats access to energy as an essential service, so a supplier must first offer alternatives, such as Fuel Direct (deductions from benefits), an instalment repayment plan, or a prepayment meter, before disconnection is even considered.
  • Fitting a prepayment meter without the customer's agreement is tightly restricted. Ofgem's rules, part of every supplier's licence since 8 November 2023, require at least ten attempts to contact the customer and a welfare visit first, and ban forced installations altogether for the most vulnerable households.
  • These rules are dual-fuel: they apply to the gas and electricity supply in the same way, which is why this box appears on both tracks.
Sources: Ofgem — Involuntary PPM Code of Practice (disconnection for debt as a last resort; the welfare and "do not install" protections); Ofgem — enhanced PPM rules (Nov 2023) (the ten contact attempts and welfare checks); Ofgem — debt strategy update (the evaluation of the 2023 rules, due to conclude in the first half of 2026).
Step 8 · Death · reversible

Meter removal & capping STATE: DEAD (DE)

A switch-off that can be undone: the meter is removed and the pipe is capped.

The first stage of winding down a gas supply is reversible. The meter comes out and the supply is capped, but the pipe stays in the ground, so gas can be restored later without a new connection. This is the amber state on the thread, and it maps to a specific UK Link status.

  • The supplier arranges for the meter to be removed and the incoming pipe capped. Once that is done the standing charge stops, and the supplier updates the central gas records to show the site is no longer taking gas.
  • The connection itself survives. The service pipe stays in place and a meter can be reinstated within a 12-month window, so the switch-off is reversible. To reflect this, the meter point status on UK Link becomes Dead (DE).
  • The meter is not the supplier's to keep. The MAP (Meter Asset Provider) owns the meter as a financed asset and recovers it when it is taken out, which ends the rental the supplier was paying.
  • A UK Link meter point carries one of five statuses: Live (LI), Dead (DE), Extinct (EX), Capped (CA) or Clamped (CL). Of these, Dead is the reversible one, which is why a capped supply sits here rather than at the terminal end.
  • One nuance on reversal. If a meter point was set to Dead in error, and the supply was never physically disconnected, a Dead-to-Live (DTL) request can restore it. If the service was truly cut and a new supply laid, DTL is not appropriate and a new MPRN is issued instead.
Sources: Xoserve — Shipper Pack Guidance Document (the LI/DE/EX/CA/CL status set); Xoserve — M Number Creation (Dead status & Dead-to-Live); Octopus — disconnecting your gas supply (the 12-month window).
Step 9 · Death · the point of no return

Permanent disconnection STATE: DEAD (DE) · IRREVERSIBLE

The permanent cut: the service pipe is dug up, cut and sealed at the gas main.

Permanent disconnection is the point of no return for a gas supply. Capping leaves the pipe in place; this cuts it off from the main.

  • Only the gas transporter that owns the pipes (a GT or iGT), or an accredited UIP working to its rules, may do this. The work means digging down to the main, then cutting and sealing the service pipe. It is normally needed before a building can be demolished.
  • There is also a safety rule behind the timing. Under the Gas Safety (Installation and Use) Regulations, if no meter has been refitted within 12 months and there is no service valve, the pipe must be disconnected as near to the main as is practical and sealed at both ends, so a disused pipe cannot become a hazard.
  • The word "disconnected" here describes the pipe, not a UK Link status. In the data the meter point stays Dead (DE) until the Transporter formally makes it Extinct (EX). The practical difference from capping is that once the service has truly been cut, a Dead-to-Live request is no longer legitimate.
  • As with electricity, there is no shortcut back. Restoring gas to the site means applying for a brand-new connection, which starts the whole journey again from the top.
Sources: Cadent — gas disconnections; LRQA — Gas Industry Registration Scheme (accredited UIPs may carry out disconnections); Gas Safety (Installation and Use) Regulations 1998 (the 12-month service-pipe rule); Xoserve — Shipper Pack Guidance Document (the Dead-to-Extinct status transition).
Step 10 · Death · retirement

MPRN retirement STATE: EXTINCT (EX)

The MPRN is closed for good and the last pipework removed. The thread ends.

The final step closes the record on the gas side. The identifier is closed for good and the last pipework removed.

  • Once the 12-month reinstatement window has expired, the Gas Transporter removes any remaining pipework and terminates the MPRN, which sets its UK Link status to Extinct (EX).
  • An Extinct MPRN is never reused, so a future gas connection at the same address gets a new one. If no other property in the postcode still has a live gas connection, the postcode can then appear on Xoserve's Off-Gas Postcode Register, a list of postcodes where Xoserve has no record of an active gas connection.
  • For a demolition, the gas meter must be removed first so that any gas left in the pipework can be safely cleared. This is legally required, because trapped gas on a demolition site is dangerous.
Sources: Xoserve — Shipper Pack Guidance Document (the Extinct status); Xoserve — Supply Point Administration (the Off-Gas Postcode Register); NFDC — Disconnection of Services (DRG108) and CDM Regulations 2015 (removing services before demolition); Octopus — disconnecting your gas supply (the domestic decommission journey).
MPAN · Not yet created